Facilities

Progress Reports

Facility progress reports are emailed to parents and staff through HPISD's eNewsletter. Each update is posted below - click the links to view the full version of each article. 


September 15, 2017

New Elementary School

Highland Park ISD’s first new elementary school since 1948 opened on time for the students of University Park Elementary School on August 28. The school features classroom pods for each grade level, flexible learning spaces, larger classrooms, an outdoor learning garden and appropriately sized core spaces, such as the library, cafeteria and gymnasium. Minor items to close out the construction project are ongoing.

Below are a couple of recent photos taken at the school.



University Park Elementary School Rebuild

Piers have been poured for the new school and foundation walls will begin forming for the parking garage next week. Construction is on track for the building to open on time in August 2018. 

Below are a couple of recent photos taken at the site.


Armstrong Elementary School Renovation 

Construction on the addition and renovation is scheduled to start in December 2017.

Bradfield ES

The design for the new school continues to be developed. Meetings have been held with neighbors and several parent groups to receive feedback on the initial plan. A Legacy committee has been formed to start taking inventory of items around the school to be retained at the new Bradfield.

Renovations/Additions at MIS/HPMS

Work has begun on the tennis courts and will begin on the additions as soon as construction permits are approved.

Northwest Addition at Highland Park High School

This project is on schedule to begin construction in November, pending completion of parking lots construction.

Parking lots and playfield near High School

Construction has begun on this project and is expected to be completed in November.

Seay Tennis Center new building

Construction is underway and foundation piers are nearly complete. The foundation will be poured in the next couple weeks.

Multi-Use Building

This project is scheduled to stay in sequence with the construction completion date for the new Seay Center. Plans for the interior of the building continue to take shape.

Hyer ES

The project schedule does not start until summer of 2018. A Legacy committee has been formed to start taking inventory of items around the school to be retained at the new Hyer.

Highlander Renovations

Work to improve access for individuals in wheelchairs in the stadium student seating area was completed over the summer. The bulk of renovation work is not scheduled to start until January 2018.


August 15, 2017

New Elementary School #5

The General Contractor has completed the interior of the school, and the school will open for the beginning of the school year. The City of Dallas has installed traffic signage for the new school. Exterior landscaping is ongoing. We have had unusually significant July and August rainfall which has presented challenges. Minor punch list repair items will be ongoing.


Here are a couple of recent photos taken inside the new elementary school:






UP ES Rebuild

Demolition of the building is complete, and excavation work has begun. The City of University Park is in final review of the construction permit. The schedule is currently on track for an August 2018 opening.


Armstrong ES Renovation

Highland Park Town Council approved the zoning amendment June 26thThe project is now scheduled to start late December 2017. The overall completion schedule (which includes the renovation work) will not be affected, and the new start date is expected to result in better pricing.


Bradfield ES

Initial Schematic Design continues development. Community meetings will be scheduled in early September to receive further input from stakeholders (Legacy, PTA and neighborhood).


Renovations/Additions at MIS/HPMS

UP City Council and Town of HP City Council have approved zoning. The City has approved the permit for tennis court work. General Contractor is ready to mobilize this week.


Northwest Addition at Highland Park High School

Project is on schedule to start construction end of October (pending completion of parking lot construction). City of UP Planning and Zoning Committee recommended approval in June, and the City Council approved zoning July 18th for the Northwest addition.


Parking lots and playfield near High School

City of UP Council approved zoning for new parking lots and temporary play-field. Building permit issued, and work started. New scope requirement as a result of UP Utilities review will require new bids for additional electrical and drainage scope. Parking lot schedule has been affected by this new scope, and Contractor Lee Lewis has reworked staging so original affected Northwest area parking lot will remain open (to students) until new parking lots are constructed.


Seay Tennis Center new building

Building permit is approved, and construction work has begun. Oncor has relocated utility pole.


Multi-Use Building

Project is scheduled to stay in sequence with the construction completion date for the new Seay Center. Architects have continued to finalize plans.


Hyer ES

Project schedule does not start until summer of 2018.


Highlander Renovations

Minor ADA work at the stadium student seating area should be complete this week (only installation of handrails remains for completion). Bulk of renovation work is not scheduled to start until January 2018.


June 13, 2017

New Elementary School

The General Contractor for the new school, Balfour Beatty, continues to make progress, and the school is on schedule to open for the beginning of the school year. Oncor set the power poles for permanent power, and the building should be energized by the end of the week. Interior wall partitions are almost completed in all areas. Walls are textured and painted in all floors of Area A, and the tile wainscot is installed in the corridors. Ceiling grid and lights installation is almost complete. Bathroom tile is ongoing in the building. Casework in classrooms is ongoing. Kitchen equipment continues installation and kitchen flooring is currently being installed. Stonework and brickwork continues. Exterior storefront doors are nearing completion. Permanent roof has been completed. Sidewalk installation on Durham is nearly complete. Queue lane construction has started

Here are a couple of recent photos that we’ve taken of the site. The public can monitor progress online with the camera that has been placed at the location. Still photos and time-lapse photography of the project are available. 


     


UP ES Rebuild

Balfour Beatty is currently scheduled to begin demolition the week of June 19thAsbestos abatement is ongoing. Construction barricades have been installed around the school. Neighborhood meeting conducted June 7th. Neighbor comments incorporated in development of final construction staging plan. Contractor will enter construction truck traffic from Lovers, and exit site from Thackery or Lovers.  


Armstrong ES Renovation 

The project schedule has been revised (with input from Construction Manager Balfour Beatty) and construction is now scheduled to start late December 2017. The overall completion schedule (which includes the renovation work) will not be affected, and the new start date should result in better pricing. Work session with Highland Park Town Council is scheduled for June 20th.


Bradfield ES

Schematic Design started immediately following the April 4th community meeting. 


Renovations/Additions at MIS/HPMS

UP City Council and Town of HP City Council have approved zoning. Board approved GMP for this work June 6th. General Contractor ready to mobilize pending permit from City.


Renovations/Additions at Highland Park High School

The project is on schedule to issue documents for bidding and construction in June 2017. City of UP Planning and Zoning Committee is reviewing the Northwest addition. City of UP Council approved zoning for new parking lots and temporary play-field. Contractor ready to mobilize pending City of UP permit approval.


Seay Tennis Center new building

Construction mobilization is anticipated to begin as soon as permit is approved.


Multi-Use Building

Project is scheduled to stay in sequence with the construction completion date for the new Seay Center. Architects continue to finalize plans.


Hyer ES

Project schedule does not start until summer of 2018.


Highlander Renovations

At called Board meeting June 6th, the Board approved a Change Order for Seay Tennis Center to accommodate pricing and schedule for ADA work in the stadium student seating area. Bulk of work is not scheduled to start until January 2018.


May 19, 2017


New Elementary School
The school is still on schedule to open at the beginning of the 2017-18 school year. Most of the mechanical and plumbing work is complete and air conditioning will be functional in the next two weeks. Interior walls are being installed, textured and painted. Kitchen equipment is being installed and the permanent roof has been completed. Stonework and brickwork continues with many areas complete. A street resurfacing project has been completed and work on a sidewalk on Durham from the school south to Caruth has begun.
 
Monitor progress online and watch a time-lapse video by visiting: https://app.oxblue.com/open/highlandpark


University Park Elementary School Rebuild
Friday, May 19 is the last day of school for University Park Elementary School in its current building. Wednesday's send-off celebration for the school was attended by many former students and teachers. Teachers will pack up and move their items out on Monday and Tuesday of next week.
 
An online auction for items from the school brought in more than $66,000 to the district. Those who bid the highest on particular items will be able to pick them up next week. Following the removal of asbestos, the school will be torn down starting in mid-June to make way for the new one, which will feature more classroom space, more play space for students, flexible learning spaces, underground parking and a more attractive entry off of Amherst to the north.
 
Armstrong Elementary Renovation
With input from Construction Manager Balfour Beatty, the project schedule has been revised so that construction will begin in late December 2017. The overall completion schedule (which includes the renovation work) will not be affected, and the new start date is expected to result in better pricing on the project.
 
Bradfield Elementary
A legacy committee has begun work on identifying certain items from the school that will be important to maintain its rich tradition. Architects have started work on preliminary designs following meetings with neighbors, the Bradfield legacy committee and the district's Design and Construction committee.
 
Renovations and Additions at MIS/HPMS
This project is on schedule to issue for bidding this month, following approval by the City Council earlier this week. The Highland Park Town Council will not hear this case until June.
 
Renovations and Additions at Highland Park High School
The project is on schedule to issue documents for bidding and construction in June 2017. The conceptual master plan of the HPHS site has been submitted to the city of UP. Zoning for new parking lots and a temporary playfield near the district's administration have been approved by the UP City Council.
 
Seay Tennis Center new building
Once a final building permit is approved, work should begin on the site. Construction mobilization is anticipated to begin as soon as permit is approved. 

Once construction begins, there will be no access to the HPHS Parking Garage and HPISD Outdoor Tennis Center via Glenwick Lane. While construction continues for the foreseeable future, access to the HPHS Parking Garage will only be available via Westchester Drive.

 
 
 Renderings of the Multi-Use Building


Multi-Use Building
The district's Design and Construction Committee reviewed plans for the multi-use building this week. A few of the renderings are below. In addition, the architect continues to work on relocating the proposed Training Room into the existing Baseball Locker Room Building. The project has been rescheduled to stay in sequence with the construction completion date for the new Seay Center.


Hyer Elementary
Although the project schedule does not start until summer of 2018, a legacy committee will be formed during the next few months to begin taking an inventory of items to be kept while Hyer is under construction.
 
Highlander Stadium Renovations
Work is not scheduled to start until January 2018.



April 7, 2017

   

The following is a status report of where several projects stand as of early-April:

 
Construction on the new elementary school near Northway Christian Church
The new school continues to take shape and remains on schedule to open in August. Bricks are being laid, roofing is being installed and interior wall partitions are being set in place. Construction on a sidewalk along the west side of Durham to the school will be completed in time for the beginning of the school year in August.
 
University Park Elementary School Rebuilding Project
The design of the new campus has been approved by the University Park City Council. Plans for the underground parking garage, which will enter from the south from Lovers Lane, has been expanded to provide 85 spaces. The school is on target to begin construction this summer. A legacy committee has identified various items at the current school that will be kept and eventually moved into the new school upon completion.
 
Armstrong Elementary School Renovation
Plans for the renovations are nearly complete. Construction is planned to begin in late-summer 2017.

Bradfield Elementary School Rebuilding Project
Work on the schematic design for the school will begin this summer. A legacy committee is being formed to review items at the school that should be kept and moved to the new school upon completion.
 
Renovations/Additions at MIS/HPMS
Plans for additions to the middle school have been finalized and will require approval from both the City of UP and Town of HP. If approved, construction will begin in the fall.
 
Renovations/Additions at Highland Park High School
The new Seay Tennis Center, to be located east of the high school parking garage, will begin construction later this spring. This project will eventually allow a new multi-use building, to include a natatorium, to be built on the site of the existing tennis facility. Construction on the additional classrooms on the northwest corner of the high school (just north of the band hall) is scheduled to begin summer 2017.



March 3, 2017

The following is an update on what has taken place throughout the district:
 
New Elementary School

The school is still projected to be completed in time for the 2017-18 school year. As of Friday, March 3:
  • The first floor garage deck is completed. Plumbing and lighting conduit is being installed in the garage. Masonry work for the gym is complete, moisture barrier has been installed (the bright teal color) and stonework has started. Area C interior walls are being installed.
  • All floors for Area A have been poured. HVAC duct and electrical conduit is almost complete on the first floor, and is being installed on the second and third floor. HVAC unit screening is installed on the roof deck. Roofing installation work has begun
  • In Area B, all steel is in place and all floors have been poured.
  • Windows frames are being installed in Areas A and C.

The public can monitor progress at any time online with the camera that has been placed at the location. Still photos and time-lapse photography of the project are available.
 
University Park Elementary Rebuild

  • Design Development documents have been completed, and the contractor, Balfour Beatty, is working collaboratively with the architect to refine the estimates. The parking garage design has been expanded to accommodate all staff from the school.
  • The design submittal was approved during the City of UP Planning and Zoning meeting, and is now scheduled for a hearing before the UP City Council on March 21.
  • The construction drawings are scheduled to be completed and ready for bidding in early April 2017. 

Click here to read the full March 2017 Facilities Update.



Dec. 16, 2016

Progress continues to be made on new facilities in Highland Park ISD.  Much of the foundation for the new elementary school near Northwest Highway has been poured and the steel frame for all floors is being installed. In addition, the contractor has started work on installing a larger storm sewer to resolve water run-off issues in the neighborhood.

Below are recent photos from the site:



Plans for the new University Park Elementary School are taking shape. The new design will incorporate some of the school's existing features (including the frontispiece surrounding the current front door) and provide significantly more active green space for students and the community. All classrooms and common areas, such as the cafeteria and gymnasium, will be larger, there will be underground parking for staff and the school's exterior facing Amherst will be a vast improvement over what is there currently.
            
Below are initial renderings of the plans for the new University Park Elementary School:

 
Lovers Lane Entrance 
 
 
Amherst Ave. Entrance 


Click here to read the full Dec. 2016 Facilities Update.


Oct. 28, 2016


Highland Park ISD continues to make progress with design and construction related to the $361.4 million bond election approved by voters in November 2015. A bond project schedule is now available online - click here to view it.

The general contractor for the new school, Balfour Beatty, is pouring concrete for the parking garage. Pier installation has been taking place on the rest of the building and the public should start to see the school begin to take shape in the next few weeks.The sanitary storm line installation in Wentwood Drive is complete and Northway Christian Church is connected to the new sewer.

A camera has been installed at the location to make available still photos and time-lapse photography. The camera is available at https://app.oxblue.com/open/highlandpark. In addition, a detailed construction schedule (subject to change based on weather conditions) has been posted on the district's website - click here to view it.

Click here to read the full October Facilities Update.


June 23, 2016

Ground has been broken and demolition has begun at the site of Highland Park ISD's first new elementary school since 1948. That and other projects are beginning to take shape as part of HPISD's $361.4 million bond election approved by voters in November 2015.

Here's an update on progress:

The HPISD School Board, Superintendent Dr. Tom Trigg and Dallas City Council Member Jennifer S. Gates officially broke ground June 20 on the first new elementary school in HPISD since 1948. 


New elementary school Highland Park ISD officially broke ground June 20 on a new elementary school designed to serve students for generations to come. Approximately 200 community members gathered at the site of the new school, on the corner of Wentwood and Durham, to celebrate as construction begins on the state-of-the-art facility for HPISD students. Click here to view a photo album from the event.  

After the groundbreaking ceremony, Balfour Beatty Construction began clearing the site to prepare for construction. The firm has installed a screening fence and will use the north part of the site to stage and enter the property. Every effort, within reason, will be made to limit parking on residential streets during the construction stage of the building. In addition, a 24-hour hotline has been established for neighbors to be able to report concerns related to construction. (Click here to see the construction plan for the site.) The school is scheduled to open in August 2017.

To read more about the June 23, 2016 Facilities Update, click here.



March 31, 2016

Highland Park ISD continues to make progress toward starting construction related to the $361.4 million bond election approved by voters in November 2015.
 
The following is an update on what has taken place so far:
 
Bond sale
In February, the district sold $225 million in bonds with a 20-year amortization at an interest rate of 2.95%, well below the 4.5% interest rate prior to the November bond election. By taking advantage of such a low rate, HPISD taxpayers will pay less than initially expected. The 2016-17 tax rate will be released in August.
 
New elementary school
Significant progress has been made on plans for the district's first new elementary school in nearly 70 years. Several focus groups have provided input on both the exterior and interior design of the school and the board has received two updates from the district's architect. 
Click below to view the most recent School Board presentation.

In addition, the district has been working with officials from the City of Dallas regarding the permitting and zoning for the new school as well as the traffic plan around the site. While final approval will still be needed from the Dallas City Council, the district remains on track to begin construction in early summer.

Construction firms
Following a competitive process, the firm of Balfour Beatty was selected to handle construction related to the bond program at all of the district's elementary schools. A second competitive process has begun to select a construction firm to work on additions/renovations to McCulloch Intermediate School/Highland Park Middle School and Highland Park High School.

To read more about the March 2016 Facilities Update, click here.


January 25, 2016

Progress continues to be made in laying the groundwork for several major projects approved by HPISD voters in the 2015 bond election.
 
The following is an update on plans for the district's facilities:
 
Upcoming bond sale
The Finance Committee of the HPISD School Board held a public meeting Jan. 14 to discuss, in part, the timing and sale of bonds to finance the construction projects. With the counsel of the district's bond market advisor, the committee reviewed several options and determined that selling $225 million in bonds with a 20-year amortization would be the most prudent course of action. Contributing to the decision is a very favorable bond market and HPISD's "Aaa" rating from Moody's Investor Service. The School Board has authorized the administration to sell the bonds with a sale expected to take place in February.
 
If the sale goes as anticipated, the tax rate increase is expected to be less than what was initially projected prior to the election. Look for further updates on the bond sale in February.
 
5th elementary campus
HPISD is continuing to work with Northway Christian Church to purchase land for a fifth elementary school. The talks are going as scheduled and the sale of property is expected to be completed this spring.
 
Designs for the school are still in the preliminary stage, and HPISD administrators are working with architects and focus groups on the layout of the interior of the campus. It is expected that the initial designs for the building will be presented at the Feb. 9 School Board meeting. 
 
HPISD has engaged the services of Masterplan to assist with the permitting and zoning for the new elementary campus, which will be located within HPISD's boundaries and the City of Dallas. Masterplan has worked with hundreds of schools throughout Dallas to ensure that they met City Hall's requirements.

To read more from the January 2016 Facilities Update, click here.


December 4, 2015

The planning process is underway so that construction can soon begin on several of the major projects approved by voters during last month's bond election.
 
Throughout November, HPISD administrative staff held several planning meetings to begin mobilizing the necessary resources to implement the projects envisioned by the HPISD Board of Trustees and the Facilities Advisory Committee.

"These past few weeks have been critical to us as a school district administration to figuratively lay the groundwork so that construction can begin in earnest on the new elementary school this spring," said HPISD Superintendent Dr. Tom Trigg. "While I know that we all wish that these projects were already under construction, the planning we do now will reap benefits in the future."

Click here to read the full article.